Borusan EnBW Enerji
2017 Renewable Energy Generation Investments
Pamuklu Solar Power Plant
Mut - Mersin
Leading aspects of investment: We completed the project according
to our targets in terms of timing and
budget. We contributed to local econ-
omy by supplying plant equipment,
electrical equipment, piles and etc.
from local producers. We employed 8
people from local community as secu-
rity staff.
We managed to gain our country a
Timing non-agricultural land that is 40 kilo-
Start date: March 2017 meters away from the city center on
Completion date: July 2017 a slope to be utilized as solar power
plant site.
Installed Capacity
Through the lifetime of the project, 20
2.2 MW years, 3,287 tons of carbon emission
will be emitted.