lean 6
sigma projects
Company Investment Objective
Borusan Building of Building a communication center where we
Makina ve Communication can respond to and register any kind of call
Güç Sistemleri Center Project in request in order to be able to respond to
Headquarters and serve our customers in the fastest and
timely way possible.
Targeted Gains Economic: Increasing our sales
Social: Increasing customer satisfaction
Corporate: In the next step, the reconciliation process will be
improved, which is one of the reasons our customers call us
most for.
Company Investment Objective
Borçelik Flow and Increasing the burning efficiency in annealing
BAF-ArGe Thermal furnaces and saving energy
Modeling and
Optimization of
Batch Annealing
Furnace
Targeted Gains Economic: We achieved material gains.
Environmental: We consumed less natural gas and electricity.
Company Investment Objective
Supsan Supsan Engine Becoming a design partner to engine
ArGe Test Center manufacturers in valve designs, and being
able to perform validation tests necessary
for OEM
Results Economic: Through this project, our company gained the skill to
perform engine tests. We have started to perform many engine
tests inhouse, which we used to have to contract out before.
Social: Because of our test and design capabilities, we are being
preferred as valve manufacturer in new projects.
Corporate: We are among a handful of companies in the sector
who have their own test centers.